Skip to content

Anchor Shoring

You are here:Home arrow Projects arrow Shoring Projects arrow Metro Convention Centre
Metro Toronto Convention Centre | Print |
Soil anchor tieback drilling in progress by Crown Drilling Ltd., a member of the Anchor Group.
Soil anchor tieback drilling in progress by Crown Drilling Ltd., a member of the Anchor Group.

Lagged shoring complete.
Lagged shoring complete.

Lagged shoring

This subcontract was awarded to The Anchor Group and included installation of more than 100,000 ft2 of lagged shoring. The excavation extended into the shale. 350 soldier piles were installed at 10' on centre around the perimeter of the site. They were socketted into the shale below the base of the excavation. The shoring system was braced by temporary and permanent rock anchors drilled by Crown Drilling Ltd.